What operators should verify in the first maintenance cycle

The first maintenance cycle should prove that the design is stable under real load. The goal is not to “check the box” on a visit. The goal is to confirm that the cooling path, controls, and water quality are all tracking the same operating assumptions.

  • Verify CDU alarms, setpoints, and pump performance.
  • Inspect strainers, filters, valves, and leak-detection points.
  • Review trending for supply temperature, return temperature, pressure, and flow.
  • Check make-up water, conductivity, and water-treatment status where applicable.

If any of those points drift early, the system is telling you that the cadence, the controls, or the commissioning assumptions need attention. A structured inspection loop is better than a loose walkthrough because it produces repeatable evidence for the operations team.

Sources: NVIDIA Mission Control BMS integration · DOE cooling control systems · DOE cooling tower management